SKEMA ALOKASI AIR DAERAH IRIGASI SIWAYUT
Bendung |
: | Siwayut |
Sungai |
: | Siwayut |
Lokasi |
: | Kedungsari, Gebog, Kudus |
Areal Baku |
: | 661.00 Ha |
Areal Tanam |
: | 209.00 Ha |
Periode |
: | 1 - 15 Desember 2024 |
Debit Tersedia |
: | 0.145 m³/dtk |
Debit Diperlukan |
: | 0.104 m³/dtk |
Faktor K Rencana |
: | 1.00 m³/dtk |
Q Renc. Dialirkan |
: | 0.104 m³/dtk |
KETERANGAN :
A | |
---|---|
B | ha |
C | A.Tanam |
D | m³/det |
E | m³/det |
: | Nama Petak Tersier |
: | Luas Petak Tersier |
: | Areal Tanam Periode ini |
: | Kebutuhan air |
: | Rencana Pemberian air |
G
H
H
SKEMA ALOKASI AIR DI. SIWAYUT
Bendung |
: | Kedungwaru |
Debit Tersedia |
: | 0.145 m³/dtk |
Sungai |
: | Kedungwaru |
Debit Diperlukan |
: | 0.104 m³/dtk |
Lokasi |
: | Kedungwaru, Kunduran, Blora |
Faktor K Rencana |
: | 1.00 m³/dtk |
Areal Baku |
: | 661.00 Ha |
Faktor K Real |
: | 0.00 m³/dtk |
Areal Tanam |
: | 209.00 Ha |
Q Renc. Dialirkan |
: | 0.104 m³/dtk |
Periode |
: | 1 - 15 Desember 2024 |
Q Real. Dialirkan |
: | 0.000 m³/dtk |
KETERANGAN :
A | |
---|---|
B | ha |
C | A.Tanam |
D | m³/det |
E | m³/det |
F | m³/det |
: | Nama Petak Tersier |
: | Luas Petak Tersier |
: | Areal Tanam Periode ini |
: | Kebutuhan air |
: | Rencana Pemberian air |
: | Realisasi Pemberian air |
G
H
H
0.083
0.051
0.051
0.083
0.052
0.052
0.082
0.051
0.051
0.026
0.016
0.016
0.081
0.050
0.050
0.072
0.045
0.045
0.078
0.049
0.049
0.034
0.021
0.021
0.045
0.028
0.028
0.059
0.036
0.036
0.036
0.022
0.022
0.018
0.011
0.011
0.016
0.010
0.010
0.008
0.005
0.005
0.006
0.004
0.004
SWT.5.ka | |
---|---|
24.00 | ha |
10.00 | A.Tanam |
0.004 | m³/det |
0.002 | m³/det |
SWT.9.ka | |
---|---|
17.00 | ha |
4.00 | A.Tanam |
0.002 | m³/det |
0.001 | m³/det |
SWT.1 | |
---|---|
15.00 | ha |
3.00 | A.Tanam |
0.001 | m³/det |
0.000 | m³/det |
SWT.3 | |
---|---|
24.00 | ha |
10.00 | A.Tanam |
0.004 | m³/det |
0.002 | m³/det |
SWT.6.ka | |
---|---|
104.00 | ha |
34.00 | A.Tanam |
0.014 | m³/det |
0.008 | m³/det |
SWT.11.ka | |
---|---|
27.00 | ha |
10.00 | A.Tanam |
0.004 | m³/det |
0.002 | m³/det |
SWT.15 | |
---|---|
71.00 | ha |
15.00 | A.Tanam |
0.006 | m³/det |
0.004 | m³/det |
SWT.14 | |
---|---|
28.00 | ha |
5.00 | A.Tanam |
0.002 | m³/det |
0.001 | m³/det |
SWT.13 | |
---|---|
39.00 | ha |
19.00 | A.Tanam |
0.008 | m³/det |
0.005 | m³/det |
SWT.12 | |
---|---|
36.00 | ha |
6.00 | A.Tanam |
0.002 | m³/det |
0.001 | m³/det |
SWT.11.ki | |
---|---|
31.00 | ha |
11.00 | A.Tanam |
0.004 | m³/det |
0.003 | m³/det |
SWT.8.ka | |
---|---|
59.00 | ha |
22.00 | A.Tanam |
0.009 | m³/det |
0.005 | m³/det |
SWT.10 | |
---|---|
62.00 | ha |
20.00 | A.Tanam |
0.008 | m³/det |
0.005 | m³/det |
SWT.4 | |
---|---|
31.00 | ha |
7.00 | A.Tanam |
0.003 | m³/det |
0.002 | m³/det |
SWT.5.ki | |
---|---|
26.00 | ha |
5.00 | A.Tanam |
0.002 | m³/det |
0.001 | m³/det |
SWT.2 | |
---|---|
31.00 | ha |
7.00 | A.Tanam |
0.003 | m³/det |
0.002 | m³/det |
SWT.7.ka | |
---|---|
85.00 | ha |
35.00 | A.Tanam |
0.014 | m³/det |
0.009 | m³/det |
Coptyright © 2019 - Tim Sisda Balai PSDA Seluna